Ksilotek-Sibir (Segezha Group)

Description of work

Having been general contractor of the project and supplier of all the necessary equipment for pellet manufacture, we currently ensure supply of spare parts and consumables for the operating pellet plant, using our unique terms of cooperation with European machinery producers and stock facilities in Tallinn and St. Petersburg.

Project timeline
2018 - present time
Customer reference
Ksilotek-Sibir LLC is creating a new timber processing facility with a full processing cycle in Lesosibirsk, which is realised within the framework of investment project of the total value over 1.2 bln rubles 'Development of Full-cycle Woodworking Complex in the town of Lesosibirsk'. The project implementtion will ensure complex use of forest resources, as well as disposal of residuals by means of biofuel (wood pellets) manufacture  and heat power generations. The launch of the first two production lines (capacity of 70 thousand tons of pellets) took place in December 2018. The construction of the third line started in August 2019, and already in December 2019 the third pellet plant producing 4.5 tons of pellets per hour was put into operation.